Progress Update

Have you noticed that the construction fence is now removed?!  That’s a definite sign of our moving closer to an opening date!

The Co-op Team has been working almost 24/7 pushing, pulling, and installing store equipment.  Some key progress notes are:

  • Many inspections will be done in August.  Inspections are being recorded manually until Loudoun County reopens the process with their new system upgrade.  Then, we hope to be at the top of the list for final occupancy inspection!
  • Interviews for our permanent General Manager are being conducted.  The search committee is very impressed with the quality of candidates; and, a selection will be made soon.
  • The refrigeration cases are installed, operating, and being tested.
  • The deli countertops and the office desks have been installed.
  • The fire suppression system is being tested.
  • Our Working Dog Cafe’ signage should be installed very soon.

Meat slicers and ovens ready to go; grocery carts ready to roll!